Hello - I'm working on a project I can't wrap my brain around this and am hoping to get some help here.
We have a scanning project that involves the 3 tasks of prepping, scanning and reassembling files.
Given the following information:
Total Files = 650
Employees = 5
Number of Hardware Scanners = 3
Prepping – 3 files per hour
Scanning – 5 files per hour
Reassembling – 3 files per hour
What is the formula/algorithm to determine how to best utilize the staff to get all 650 files prepped, scanned and reassembled in the least amount of time? i.e. # of staff performing each task for X period of time/# of files before shifting staff to other tasks.