Hello - I'm working on a project I can't wrap my brain around this and am hoping to get some help here.
We have a scanning project that involves the 3 tasks of prepping, scanning and reassembling files.
Given the following information:
Total Files = 650
Employees = 5
Number of Hardware Scanners = 3
Prepping – 3 files per hour
Scanning – 5 files per hour
Reassembling – 3 files per hour
What is the formula/algorithm to determine how to best utilize the staff to get all 650 files prepped, scanned and reassembled in the least amount of time? i.e. # of staff performing each task for X period of time/# of files before shifting staff to other tasks.
Any help would be greatly appreciated. I am working on this in excel now.
Thank you!
-
June 18th, 2013, 12:57 PM
#2
Re: Staff Utilization Algorithm
Forgot to add above that each employee is working 40 hours per week
-
June 19th, 2013, 07:18 AM
#3
Re: Staff Utilization Algorithm
sounds like a basic priority queue thing... each hour you reallocate personel according to the priorities (i.e. try to make sure your bottlenecks are as close to 100% activity the whole time)
put at most 3 people on scanning in so far as you can give each person the 5 files for that hour
if you still have files to prep, put everyone else on prepping in so far as you can give each one 3 files to prep (except the very last pile of files which won't be complete)
if you still have files to reassemble put whatever personel you have left on reassembling
Posting Permissions
- You may not post new threads
- You may not post replies
- You may not post attachments
- You may not edit your posts
-
Forum Rules
|
Click Here to Expand Forum to Full Width
|